Construction continues at a pace at MIRA

Construction continues at a pace at MIRA

Haldex is well underway on site with the floor slab steel frame and roof completed and the wall cladding finished.

Building 3 is fast catching up with the Haldex building, the steel frame is complete, the floor slab almost complete and the wall cladding started.

Accelerator Building (MAB1) is just about to commence on site. Site strip has already started and the steel frame is ordered.